The Wire Doctors · Technical Specifications · WD5803

200 Amp 20–40 Circuit Service Upgrade

2020 National Electrical Code (NEC) References

01. Service Equipment

Remove/modify as needed; install 200 A, 20 to 40-circuit panel with appropriate single/double-pole breakers; Meter Base with Connected Emergency Disconnect per NEC 230.85; up to 35 ft SEU with proper routing.

NEC Article 230 — Service Equipment and Disconnects

02. Surge Protection

Whole Home Surge Protector per NEC 230.67; test and label.

NEC Article 230

03. Grounding & Bonding

Install/verify grounding electrode system (primary/secondary), bond cold water piping within 5 ft of entry, bond water meter, and install ISBT in line with the grounding electrode conductor.

NEC Article 250

04. Wiring & Safety

Route conductors in approved enclosures/raceways; de-energize; generalized labeling and circuit mapping.

NEC Articles 210–240; 250–300

05. Testing & Documentation

Verify proper voltages and disconnect operation.

06. Exclusions

Anything beyond 200 A/20 to 40 circuits, cosmetic work, or utility fees not specified.

Code Compliance Notes

The above references align with the 2020 NEC structure. Confirm any local amendments with the Authority Having Jurisdiction (AHJ).